To do:
Matt:
- Matt will set up a recording session for the 4 Matas next week
- Set up auditions for other singers later this or next week or a tape of them singing the songs.
- Purchase Jam Pack for songs at bookstore
- ask the boys to work on embellishing the 3D environs as we can.
Barb:
- Barb will write Sherwin (at CMI) so that we can record up there in their *hopefully finished by now* room
- Barb will work on the text for the experiment dialog.
CC:
- Mock up walk around island with 4-6 sick pirates and each pirate will have 4 possible dialogues/jokes.
- BARB'S NOTES: CC thinks we need to embellish the 3 d environments for the walk around. He is going to have pirates that offer jokes, and work on an interface so that we know how they walk around. At some point, we can have the pirates give blurbs about content if needed. (but one way blurbs only, no interaction). With stepped through, location specific text that they offer. He'll plan on it being onscreen text with eventual plans to turn into audio.
Gerrit, James (Kyle & Logan if needed)
- Work on the IVDV 10 item test
Kyle & Logan:
- - Matt will ask the boys to work on embellishing the 3D environs as we can.
Songs Update:
Tiki & Hermit to a point can't where animation can't continue until we get the songs.
- Gerritt has tested how well a flash movie plays inside shockwave... so far so good on faster machines. On older macs, not so much... We're still clearly developing for "new" machines. The Carl Winter movies (at 30 fps) were pokey. We still think we'll be ok at 15 fps... and we're going forward as planned.
- The midi files work... we can open them and use them.
- In production on song animations... but at a stopping point without final audio.
- 4 Matas should be ready to record next week. Matt will set up recording time.
Matt:
- Matt will set up a recording session for the 4 Matas next week
- Set up auditions for other singers later this or next week or a tape of them singing the songs.
- Purchase Jam Pack for songs at bookstore
- ask the boys to work on embellishing the 3D environs as we can.
Barb:
- Barb will write Sherwin (at CMI) so that we can record up there in their *hopefully finished by now* room
- Barb will work on the text for the experiment dialog.
CC:
- Mock up walk around island with 4-6 sick pirates and each pirate will have 4 possible dialogues/jokes.
- BARB'S NOTES: CC thinks we need to embellish the 3 d environments for the walk around. He is going to have pirates that offer jokes, and work on an interface so that we know how they walk around. At some point, we can have the pirates give blurbs about content if needed. (but one way blurbs only, no interaction). With stepped through, location specific text that they offer. He'll plan on it being onscreen text with eventual plans to turn into audio.
Gerrit, James (Kyle & Logan if needed)
- Work on the IVDV 10 item test
Kyle & Logan:
- - Matt will ask the boys to work on embellishing the 3D environs as we can.
Songs Update:
Tiki & Hermit to a point can't where animation can't continue until we get the songs.
- Gerritt has tested how well a flash movie plays inside shockwave... so far so good on faster machines. On older macs, not so much... We're still clearly developing for "new" machines. The Carl Winter movies (at 30 fps) were pokey. We still think we'll be ok at 15 fps... and we're going forward as planned.
- The midi files work... we can open them and use them.
- In production on song animations... but at a stopping point without final audio.
- 4 Matas should be ready to record next week. Matt will set up recording time.